Case Study #2

Date: July 2010

Client: St Mary Magdalene School, Woolwich SE18

Contractor: Lakehouse Contracts Ltd, Romford, Essex

Location: Woolwich, London

Site Details: Surrounding areas to main buildings

Area: 1000sq metres 

Lakehouse contractors were appointed to lay new tarmac to large areas alongside other associated building work around the school.

Problem:- Once the new areas of tarmac had been laid and prior to completion of the overall project, additional ground excavations had to be carried out as well as other general building work. This resulted in many areas of the new tarmac becoming stained and unsightly, where the excavation channels were filled in the overall finish of the tarmac became patchy.
 
Solution:- These problems had to be resolved and after researching the best options available, Lakehouse Contracts decided to use Tarmaseal to cover all the patchy stains and create a uniform finish as requested by the client. 

"We were delighted with the end result, and would happily use the product again. We would certainly recommend Tarmaseal to our clients and other potential users in the future." ~ James Kemp, Lakehouse contacts